Scope: Provision of equipment and personnel to erect and assemble steel roof trusses and precast concrete
Overview:
Smithbridge was awarded a project to provide equipment and personnel for the erection and assembly of structural steel members and precast concrete for an aircraft hangar.
Smithbridge mobilised five cranes and 26 personnel for the project. Over 1500t of steel was erected including 13 roof trusses were lifted into place and installed throughout the project.